Name of Project / Kind of Works:
GRD CEMENT PLANT-132/6.6kV MAIN POWER STATION
Total Value of the Contract:
100,000.00 USD
Duration:
30 days
Expected Commencement Date:
15/05/2014
Completion Date:
03/06/2014
Status of Project Completion:
100 %
Contracting Authority and Location:
Sinoma Suzhou construction Iraq company Ltd. CHINA
Prime Contractor (P) or Subcontractor (S):
P
NPC Responsibility:
Carrying out site testing and commissioning of installed equipment of 132/6.6kV Main Power Station for power supply of the GRD Cement Plant