Name of Project / Kind of Works:
132/11kV AIS, 63MVA Substation at Bazian cement plant Sulaimaniyah, Kurdistan-Iraq
Total Value of the Contract:
3,850,000.00 EURO
Duration:
10 months
Expected Commencement Date:
15/01/2011
Completion Date:
15/11/2011
Status of Project Completion:
100 %
Contracting Authority and Location:
Bazian Cement Plant – Lafarge, Iraq/Plan Co.
Prime Contractor (P) or Subcontractor (S):
S
NPC Responsibility:
Project Management, site installation works, testing and commissioning