Stage 4 Substation Project


Name of Project / Kind of Works:   Stage 4 Substation Project
Total Value of the Contract:   69,106,106,035.00 IQD
Duration:   18 months & amendment period of 143 days
Expected Commencement Date:   25/05/2009
Completion Date:   06/04/2011
Status of Project Completion:   100 %
Contracting Authority and Location:   Ministry of Electricity, Directorate of Distribution of Sulaimaniyah Governorate/Plan Co.
Prime Contractor (P) or Subcontractor (S):   S
NPC Responsibility:   Project Management