132/33 kV Suli & Super steel substation Project - Stage 2


Name of Project / Kind of Works:   132/33 kV Suli & Super steel substation Project - Stage 2
Total Value of the Contract:   695,000.00 USD
Duration:   8 months
Expected Commencement Date:   22/10/2020
Completion Date:   21/06/2021
Status of Project Completion:   100 %
Contracting Authority and Location:   Suli & Super steel Factories
Prime Contractor (P) or Subcontractor (S):   P
NPC Responsibility:   Design, Engineering Services, Delivery, Carrying out Site Erection Works, Testing, Commissioning and Energizing of Substation


Project Gallery

Your Message

© Copyright 2011 - 2024 NPC - All Rights Reserved

Designed & Developed by WAN Co.