- Name of Project / Kind of Works:
Roof top mounted Grid Tie Systems. The total installed PV capacity at the site is 16.2KWp with 30X540W JA Solar Modules, SMA Sunny Tripower 20000TL PV Inverter, Protection and Fuse Elements, three SMA Sunny Island 8.0H -13 Battery Inverter, BYD Energy Storage Battery Bank LVS 12 (36 KWh) Lithium-ion Battery with Power Distribution Unit (PDU), Battery Management System (BMS), Solarland DC Combiner box, Electrical System Distribution Board, DC & Communication Cables, Cable Trays, earthing system and all accessories and fittings.
- Total Value of the Contract:
56,997.00 USD
- Duration:
15 days
- Commencement Date:
15/03/2022
- Completion Date:
31/03/2022
- Status of Project Completion:
100%
- Contracting Authority and Location:
- Prime Contractor (P) or Subcontractor (S):
P
- NPC Responsibility:
Design, Engineering Services, Supplying, Installation, Testing, Commissioning and Energizing of the System.