- Name of Project / Kind of Works:
47KWp rooftop solar photovoltaic hybrid system at the UNFPA-Anbar Women Shelter in Iraq, featuring a 45kVA 3-phase configuration with 30kWh energy storage
- Total Value of the Contract:
112,407.00 USD
- Duration:
3 months
- Commencement Date:
23/01/2024
- Completion Date:
21/04/2024
- Status of Project Completion:
100%
- Contracting Authority and Location:
United Nations Population Fund for Iraq (UNFPA)
- Prime Contractor (P) or Subcontractor (S):
P
- NPC Responsibility:
Design, engineering services, delivery of equipment and materials to the site, carrying out site civil, mechanical and electrical installation works, testing, commissioning and energizing of 3Ph, Solar Photovoltaic Hybrid System roof top mounting type.
- Description:
"Successfully installed a 47KWp rooftop solar photovoltaic hybrid system at the UNFPA-Anbar Women Shelter in Iraq, featuring a 45kVA 3-phase configuration with 30kWh energy storage. The system comprises 84 JINKO SOLAR PV modules (Tiger Neo N-type JKM560N-72HL4-BDV, 560W) utilizing bifacial and dual glass technology, mounted on a galvanized steel structure with 69 precast concrete block footings. Key components include a PV DC string combiner box, Victron Energy Quattro Inverter/Chargers (3 units, 48VDC, 15kVA), Smart Solar MPPT Charge Controllers (7 units), and a Victron Energy Cerbo Control GX for comprehensive monitoring and control.
The installation also includes Victron Lynx Distributors, fuses, cables (AC, DC, Earth, and Communication), and associated accessories, ensuring robust connectivity and safety. Additionally, the project involved the construction of grounding and lightning protection systems. A 30kWh BYD LV Flex Lithium Iron Phosphate battery system with BMS and Communication HUB enhances energy storage capabilities.
The project was completed with thorough PV system site testing, commissioning, and startup, ensuring optimal performance and reliability for the shelter's energy needs."