Design, engineering and installation phases of the PV solar carport structures project to accommodate a total capacity of 213 KWp


- Name of Project / Kind of Works:   Design, engineering and installation phases of the PV solar carport structures project to accommodate a total capacity of 213 KWp
- Total Value of the Contract:   343,373.93 USD
- Duration:   5 months
- Commencement Date:   12/12/2023
- Completion Date:   26/04/2024
- Status of Project Completion:   100%
- Contracting Authority and Location:   United Nations Assistance Mission for Iraq (UNAMI)
- Prime Contractor (P) or Subcontractor (S):   P
- NPC Responsibility:   Design, engineering services, delivery of equipment and materials to the site, carrying out site civil, mechanical and electrical installation works, testing and commissioning.
- Description:  

This project includes two specific contracts for the installation of solar carports and associated asphalt pavement in designated parking areas within the International Zone (IZ) in Baghdad, Iraq. To provide robust and sustainable PV solar carport solutions that enhance the functionality and environmental performance of the parking areas and to ensure high-quality, durable infrastructure through meticulous design and engineering.